Brewery

The Customer: Key Production Plant to the Brewery Industry.
The Task: To re-engineer, design and supply a more efficient hydraulic power pack /hydraulic power unit within 3 days, as a major production line was down.
The solution: Within 2 hours of receiving the call one of our hydraulic engineers attended site and specified a complete, new and more efficient and powerful hydraulic power pack / hydraulic power unit. The customer issued an immediate purchase order and the hydraulic power pack was built, tested and installed within 72 hours; downtime and lost production was therefore kept to a minimum. Within a further 48 hours all lost production was recovered and orders are now being produced ahead of schedule due to greater efficiency from the hydraulic power pack.